    Quote Originally Posted by Ed_Downunder View Post
    Just to be picky and at this stage of no real consequence. Can you get footings to be pour 1. The ground floor slab to be pour 2. The 2nd floor to be pour 3?
    Edward,

    That is not how the Slab Pour Number is designed to work, so no, I can't get it to do that.

    The Slab Pour Number only applies to monolithic slabs and is applied on a room by room basis.
    This means it can't be use for the level 2 slab - the level 2 slab is separated by floor number anyway.
    I can divide the level 1 floor into 2 rooms and apply a different pour number to each - this is how it is meant to work.
    In this case, the concrete is reported separately for the footings, pour 1 (level 1), pour 2 (level 1) and level 2 slab.
    Glenn

    Chief X5
    www.glennwoodward.com.au

    Windows 7 - Home Premium
    Intel i7-920
    Gigabyte GA-EX58-UD3R
    6 Gb DDR3 1600MHz
    EVGA GTX285 1GbDDR3
    1TB Sata HD

 

 

Posting Permissions

  • Login or Register to post new threads
  • You may not post replies
  • You may not post attachments
  • You may not edit your posts
  •