03-30-2013, 03:03 AM #11
Edward,
That is not how the Slab Pour Number is designed to work, so no, I can't get it to do that.
The Slab Pour Number only applies to monolithic slabs and is applied on a room by room basis.
This means it can't be use for the level 2 slab - the level 2 slab is separated by floor number anyway.
I can divide the level 1 floor into 2 rooms and apply a different pour number to each - this is how it is meant to work.
In this case, the concrete is reported separately for the footings, pour 1 (level 1), pour 2 (level 1) and level 2 slab.Glenn