    Eyebrow dormer question

    This may be "any type" of dormer question. I have a 20'x20' pavilion with a flared hip roof and a 14" overhang. The hipped roof is 8/12. The bottom 4' has a flared pitch of 5 5/8 pitch and a radius of -154". I'm trying to install a eyebrow dormer with a round top fixed window 36"Hx72W flush with the outer wall below. No matter where I set the dormer CA won't let me install it. I've tried making it only 1/4 the size and it still won't go. Does it have something to do with the dormer starting on the flared section and extending up onto the regular pitched area? If this isn't the case I'm lost. If it is the case, is there such a thing as a work around? Are there any good videos on the subject? It's one of those frustrating days (or maybe too much coffee). Before anyone ask the plan is too large to show. As always all advice is greatly appreciated.
    Larry Sweeney
    Designer/Builder/Restorations/Period Cabinetmaker since 1972

    Chief X5, AutoCad 2010
    Windows 7 Pro
    Asus P8P67 Pro
    Intel Core i7 2600k
    8 GB DDR# 1600mhz
    GTX 670

 

 

Posting Permissions

  • Login or Register to post new threads
  • You may not post replies
  • You may not post attachments
  • You may not edit your posts
  •